skip to Main Content

A Deep Dive into PERT Estimation

PERT: What is it?

PERT is an acronym for Program Evaluation & Review Technique, and was developed by United States Defence as a quick estimating strategy in 1950’s. It is also known as Three-Point technique or PERT Weighted Average. PERT can be used to apply to Costs, and Schedules. 

 

Understanding the PERT Estimation

PERT emphasis on Three-Point estimate for each Project activity incorporating Optimistic(O), Pessimistic (P), and Most Likely (M) time estimates.

The Formula to Calculate Expected Duration (TE) for an activity is 

TE = O+4M+P

                6

This formula considers a weighted average, giving more weight to the most likely estimate. The resulting Expected Duration provides a more realistic view of the time required for an activity, considering both optimistic and pessimistic scenarios.

 

Key Components of PERT Estimation

Optimistic estimates (O):

The best-case scenario estimate, representing the minimum time required to complete an activity without any risks and favorable situation.

Pessimistic Estimate (P):

The worst-case scenario estimate, indicating the maximum time needed for activity completion Including Risks and an unfavorable situation.

Most Likely Time (M):

The most realistic and probable time estimate based on historical data and expert judgment, including favorable & unfavorable situations.

Let’s look at an example below. 

 

Sl..no.. Activities Optimistic time(O)

In Days

Most likely time (M)

In Days

Pessimistic time (P)

In Days

Expected Duration

TE = (O+4M+P)/6 

In Days

1 Requirement Analysis 10 15 20 15
2 Development 20 30 40 30
3 SIT/Functional Testing 12 18 23 18
4 UAT Testing & Support 10 15 22 15
5 Production Deployment 4 6 10 6
6 Hypercare/Warranty Period 10 15 23 16
Total TE Project 100

Table 1

Note: The above Activities can be broken down into smaller tasks. I have taken an Abstract of Activities for Illustration only.

 

Let’s Assume the Project Start Date as 06-Dec-2023

 

Sl..no.. Activities TE Start Date End Date
1 Requirement Analysis 15 06-Dec-2023 21-Dec-2023
2 Development 30 21-Dec-2023 20-Jan-2024
3 SIT/Functional Testing 18 20-Jan-2024 06-Feb-2024
4 UAT Testing & Support 15 06-Feb-2024 22-Feb-2024
5 Production Deployment 6 22-Feb-2024 28-Feb-2024
6 Hypercare/Warranty Period 16 28-Feb-2024 15-Mar-2024

Table 2

Note: Some of the above dates fall on Weekends, and this is just for Illustration Only

Now, let’s build a Timeline Chart using Table 2.

 

To Create the Timeline Chart in Google Sheets

  1. Select the above Table 2 (Data Range i.e Sheet1!C16:G22) in the example (Attached Google Sheet Below for Reference)
  2. Click on Insert → Select & Click on Timeline 
  3. Map the Column from Table 2 on Required fields (Settings) on the left pane to the following
    • Start Date -> Start Date
    • End Date or Duration -> End Date
    • Card Title -> Activities

 

Timeline Chart in Google Sheet

Link to the spreadsheet: PERT Estimation_Example

Benefits of PERT Estimation

  1. Probability Analysis: PERT estimation embraces a probabilistic methodology, offering a spectrum of potential durations for each activity. This contributes to the assessment and management of risks within the project.
  2. Improved Accuracy: PERT estimation provides a more detailed and precise depiction of project timelines when contrasted with conventional single-point estimates.
  3. Effective Resources Allocation: Project managers can better allocate resources by understanding the variability in activity durations. This promotes optimal resource utilization.
  4. Risk Mitigation: PERT estimation highlights critical path activities and potential bottlenecks, allowing project teams to focus on risk mitigation strategies.

By embracing the three-point/PERT estimation methodology, Project Managers/Sales/Developers/Testers can navigate uncertainties, enhance decision-making, and steer their teams toward successful project completion. PERT estimation is not merely a mathematical tool; it’s a strategic ally in the pursuit of project success, offering a holistic view that empowers teams to adapt, innovate, and thrive in the face of complexity.

Visit our blog, here
View our LinkedIn, here

Sunil has 16 years of experience in BI, DWH, DB, UI testing and project delivery across Healthcare, Insurance, Banking, & Telecom industries. Currently Working with Mindset as a Project Delivery Lead, Sunil likes to learn new technologies, and follow current trends. He enjoys going on long drives, trekking, playing badminton, & listening to music.

Back To Top